HSR Campus Project

Last Updated:

2022-06-24

Project Name Progress Description
High-Speed Rail Campus Area 1. Phase 1 Progress: The architectural planning report was submitted to the university on September 16, 2019, and approved on September 24, 2019. Before December 26, 2019, Phase 1 detailed design was submitted. After three budget review and working meetings, the first revision of Phase 1 detailed design was submitted in March 2020. Joint expert review conducted April 7, 2020. Procurement review and preliminary meeting held July 8, 2020. Public inspection August 28, 2020, and four public tenders on September 22, September 30, October 12, and October 20, 2020, all resulted in no bids. On November 3, 2020, correspondence sent to the architect for budget and schedule review. First revised tender November 10, 2020, no bids; second tender held December 9, 2020, one bid received. The bidder (Kuo Fang Construction Co., Ltd.) met qualifications. Qualification passed review December 15, 2020. Price bid opened December 24, 2020, but declared void due to quote exceeding base price. Third tender announced December 25, 2020; opened December 31, 2020, no bids received. Review meeting January 6, 2021; revised budget submitted January 12, 2021. Second revised tender opened February 25, 2021, no bids. Second tender opened March 9, 2021; evaluation March 16, 2021. Kuo Fang Construction entered price bid stage March 18, 2021; bid NTD 207,168,000 (after discount), exceeding base price NTD 205,050,000 by NTD 2,118,000. Award announced on-site according to Article 53, Paragraph 2 of Government Procurement Act.

Construction began April 26, 2021, with a period of 510 calendar days. Extended 42.5 days due to pandemic and rain; 7 days excluded for Lunar New Year. Expected completion November 6, 2022. As of June 19, 2022, works include 23 rooftop and exterior wall works of the practice shed, first-floor roof and wall of sewage treatment plant, first-floor interior renovation of main power distribution and water tank, and sterilization work. Scheduled progress 50.16%, actual 56.60%, cumulative 413 days, remaining 140 days.

2. Phase 2 Progress: The architectural planning report submitted December 2, 2019, finalized for reference. Detailed design began December 13, 2019. Draft submitted April 20, 2020, detailed design May 19, 2020. Detailed design review meeting October 16, 2020. Corrected budget submitted November 23, 2020; reviewed by third-party notary (Taichung Structural Engineers Association) December 14, 2020, and January 29, 2021. Corrected submission March 18, 2021; third-party review completed April 19, 2021. Procurement strategy meeting May 6, 2021; budget gap addressed. Corrected concept submitted May 21, 2021; approved June 23, 2021 (Taiwan Ministry of Education approval no. 1100078112). Technical service price negotiation July 15 and 22, 2021; contract and detailed design completed. Procurement review September 13, 2021. Tender method (most advantageous bid) and combined tender approved by Ministry. Public inspection November 26, 2021; first and second public tenders December 7, 2021, and January 21, 2022, no bids. Corrected first tender in same month, no bids. Second announcement received one bid; evaluation meeting scheduled July 4, 2022.